| Project Name | Jintang Port Area Taipukou Container Terminal Project Stage II Embankment and Land Formation Works | ||
| Project Location | Zhoushan, China | Engineering Costs | About 55 million yuan |
| Start time | June, 2014 | Completion time | December, 2016 |
| Company | Name | ||
| Owner | Zhoushan Yongzhou Container Terminal Co., Ltd | ||
| Design | CCCC Shanghai Waterway Survey and Design Institute | ||
| Supervisory | Ningbo Port Engineering Project Management Co., Ltd | ||
| Project Overview | |||
The new embankment is 1,158 m in length, with a riprap structure, 2T accropodes revetment, and a reinforced concrete wave breakwater protecting surface of the top of the embankment with slurry masonry blocks wrapped around it, with a sand-filled pipe bag anti-filtration layer inside. The dike is filled with 1.8 million m³ of blown sand, forming a land area of 261,000 ㎡. | |||

Overall Layout Rendering of the Project

Groundbreaking Ceremony

Offshore Mattress Laying Vessel Operation

Offshore Vibroflotation Plate Insertion Vessel Operation



2-Ton Accropode Unit Prefabrication at the Precast Yard


Foundation Cushion Layer Concrete Casting for the Wave Wall on the Dike Crest



Ningbo Xiaolang Construction Engineering Co., Ltd.
Ningbo Tianyuan Cement Products Co., Ltd.
Yuehu Ginza, Nanzhan East Road, Haishu District, Ningbo City
+86 574 8698 8331
315012
Copyright © Ningbo Tianyuan Construction Engineering Co., LTD All Rights Reserved | Sitemap
