| Project Name | Section A of the Inner Lake West Bank Yuewan Residential Area Quay Wall Project | ||
| Project Location | Haicang District, Xiamen | Engineering Costs | RMB 5.9576 Million |
| Start time | October 2006 | Completion time | June 2007 |
| Company | Name | ||
| Owner | Xiamen Haitou Engineering Construction Co., Ltd. | ||
| Designer | CCCC Third Harbor Consultants Co., Ltd. | ||
| Supervisory | Henan Jianda Supervision Co., Ltd. | ||
| Project Overview | |||
The Xiamen Haicang Municipal Government developed a high-end residential area within the original reclaimed coastal land and carried out a lakeside rehabilitation and shoreline protection project along the Yuewan area on the west bank of the Inner Lake. The project involved soft soil foundation treatment, slope excavation, geotextile installation, dry-laid stone slope protection, finely constructed retaining walls, and granite surface finishing. The total shoreline length was 200 m, with 5,500 m³ of masonry works and 100,000 m² of geotextile installation. | |||


Landscape Stone Slope Protection
Ningbo Xiaolang Construction Engineering Co., Ltd.
Ningbo Tianyuan Cement Products Co., Ltd.
Yuehu Ginza, Nanzhan East Road, Haishu District, Ningbo City
+86 574 8698 8331
315012
Copyright © Ningbo Tianyuan Construction Engineering Co., LTD All Rights Reserved | Sitemap